
The Court of Appeal’s decision in Triathlon Homes LLP v Stratford Village Development Partnership [2025] EWCA Civ 846. handed down on 8 July 2025, confirms that a developer’s well-resourced parent can be ordered to fund building safety remediation even where the works are already being paid for by the taxpayer. With the appeal to the Supreme Court having recently taken place, it is worth taking stock of what the decision means for those advising distressed property groups.
Background
The case concerned fire safety defects in the external walls of five residential blocks at East Village in Stratford, the former London 2012 athletes’ village. Stratford Village Development Partnership (“SVDP”) was the original developer and Get Living plc (“Get Living”) has in effect owned SVDP since 2018.
Triathlon Homes LLP (“Triathlon”), a social housing provider with long leases in the blocks, applied to the First-tier Tribunal (“FTT”) for remediation contribution orders (“RCOs”) under section 124 of the Building Safety Act 2022 (“BSA”). Because the developer’s group retained an interest in the buildings, paragraph 2 of Schedule 8 to the BSA meant Triathlon could not be charged for the works through its service charge. The major works were instead being funded by the Government’s Building Safety Fund (the “Fund”), under a grant of up to around £24.5m (later increased to around £27.5m).
The FTT ordered SVDP and Get Living to pay what would otherwise have been Triathlon’s share of the costs, including over £11.3m towards the forecast cost of the remaining works.
What Was the Court Asked to Consider?
Section 124 allows the FTT to make an RCO against a landlord, developer or “associated” body corporate or partnership if it considers it “just and equitable” to do so. The appeal raised two questions:
- Ground 1: whether the FTT was wrong to find it just and equitable to make the RCOs; and
- Ground 2: whether an RCO can cover costs incurred before section 124 came into force on 28 June 2022.
The Court of Appeal (Nugee LJ giving the lead judgment, with Newey and Holgate LJJ agreeing) dismissed the appeal on both grounds.
The Just and Equitable Test: Key Findings
The appellants’ central argument was that an RCO was unnecessary: the works were funded, under way and on track. The Court disagreed, holding that this took “too narrow a view” of the BSA’s purposes. As well as getting the work done, the Act answers the question of “who pays”.
- Developers sit at the top of the cascade. The BSA’s policy is that primary responsibility for remediation costs falls on the original developer. The Court noted that the Supreme Court in URS Corporation Ltd v BDW Trading Ltd [2025] UKSC 21 had endorsed this.
- Public money is a last resort. The Fund is not part of the statutory hierarchy of payers. If the Act’s mechanisms can be used, they should be, even where public funding is in place. There is no good reason for the public purse to act as “interim funder” while claims against contractors “wend their way to a conclusion”.
- No presumption, but a strong pointer. The FTT had not created an unexpressed presumption against developers with means. The Court did, however, accept that the FTT went too far in suggesting it could “ever” be unjust to leave a section 124(3) party off the hook, noting that remote associates (for example, companies linked only by a shared director) might merit different treatment.
- Parents cannot hide behind the SPV. The association provisions are aimed at a thinly capitalised development vehicle with a wealthy parent. SVDP needed Get Living’s financial support to prepare its accounts on a going concern basis, so it was “precisely” the target.
- Buyers take the liabilities. Get Living had no involvement in the development. However, the original purchasers chose to acquire SVDP itself rather than the land, and so took on its latent liabilities, including the “quite unforeseeable” risk of legislation like the BSA.
- Other claims need not come first. An applicant need not first pursue the main contractor: the RCO is an independent, essentially non-fault-based remedy, and the applicant’s motive was irrelevant.
On Ground 2, the Court held that section 124 can cover costs incurred before 28 June 2022. The “just and equitable” filter itself guards against unfairness.
What This Means in Practice
The significance of Triathlon for restructuring work lies in its reach. Under section 121, entities can be “associated” by reason of common control or shared directors at any time in the five years before 14 February 2022. The FTT has a broad discretion, and its starting point is now clearly that the group with the money pays.
Several consequences follow:
- Ring-fencing through SPVs is weaker than it looks. Insolvency of a development vehicle will not necessarily contain BSA exposure. Creditors and office-holders should expect applicants to look up and across the group.
- Contingent BSA liabilities belong in the numbers. Exposure under section 124 and under building liability orders (section 130) can be large, uncertain and retrospective. It should be reflected in cash flow forecasts, solvency assessments and, where relevant, the comparator analysis for a restructuring plan under Part 26A of the Companies Act 2006 or a company voluntary arrangement (“CVA”).
- Share deals carry history. Buyers of distressed property groups should consider whether an asset purchase offers better protection than a share purchase, and should diligence the group’s BSA history carefully. In Triathlon, the buyers’ decision to acquire SVDP rather than the land, and the earlier release of warranties from the seller, both counted against them.
Key Takeaways
- RCOs can be made against wealthy parents and associates of a developer, even where the associate had no involvement in the defects.
- The availability of public funding is not a reason to refuse an RCO; the Fund is a last resort.
- Groups with historic residential development activity should map their “associated” entities and quantify potential BSA exposure now.
- Watch this space: the Supreme Court will consider both the just and equitable test and retrospectivity.








